Answer:
Instructions are listed below.
Explanation:
Giving the following information:
Labor Estimated Hours Hourly Rate
Architect 168 $300
Staff 336 75
Clerical 725 20
Frey applies overhead to jobs at 175% of direct labor cost. Frey would like to earn at least $55,000 profit on the architectural job.
A) Total cost= architect + staff + clerical + allocated overhead
Total labor cost= 168*300 + 336*75 + 725*20= $90,100
Total cost= 90,100 + (90,100*1.75)= $247,775
B) Bid= 294,000
Profit= Bid - total cost
Profit= 294,000 - 247,775= 46,225
It will not reach the desired profit.
C) Estimated selling price= total cost + desired profit
Estimated selling price= 247,775 + 55,000= $302,775